Renovations Update
The dates listed below are very rough estimates and are subject to change

SEB 3030 and 3035
- Asbestos abatement and demolition complete
- Completion for sometime early November
 
SEB 3002 Suite - Painting and installation of new flooring underway, still waiting for one new door to be installed
- Completion by end of October
 
SEB 3105 - Furniture and electrical installation next Tuesday and Wednesday
- Should be complete by October 8
 
SEB 2093 - Some small miscellaneous items to complete, essentially done
 
SEB 2081 to 2086 - Only painting
 - Late October/early November
 
SEB 1069 - Awaiting installation of new storage cabinets
- Early November
 
SEB 1065/66 - Ready for paint
- Complete by mid October
 
Stores/Old Shop - Demolition continues
 - Completion by sometime in December