Renovations Update
The dates listed below are very rough estimates and are subject to
change
SEB 3030 and 3035 - Asbestos abatement and demolition
complete
- Completion
for sometime early November
SEB 3002
Suite - Painting and installation of new flooring underway,
still waiting for one new door to be installed
- Completion
by end of October
SEB 3105
- Furniture and electrical installation next Tuesday and
Wednesday
- Should be
complete by October 8
SEB 2093
- Some small miscellaneous items to complete, essentially done
SEB 2081
to 2086 - Only painting
- Late
October/early November
SEB 1069
- Awaiting installation of new storage cabinets
- Early
November
SEB
1065/66 - Ready for paint
- Complete
by mid October
Stores/Old Shop - Demolition continues
-
Completion by sometime in December